Evenjobb, Presteigne, Powys
 |

|
Timescale and Cost
Approx £13,500.00 supply & erect. The erection period took 2 weeks, per plot.
Thermal Efficiency
This was a project that ticked all the right boxes. For example the contractor insured the timber frame was wrapped in the higher spec breather paper and allowed for air tightness previsions during the erection stage to improve performance on completion.
Successful Project
A superior 4 bedroom luxury house, with 2 en-suits. This project was easily affordable as the design was kept to a standard straight lined concept. Keeping the footprint simple allowed the contractor to concentrate on using high spec internal finishes whilst still remaining within budget.
|

Tremile, Bwlch, Brecon
|

|
|



|
Timescale and Cost
Approx £85,000.00 supply & erect. The erection period took 4 weeks
Thermal Efficiency
This was very important to the client and was the deciding factor in using our Twin Frame System. Having the ability to achieve 0.11 W/m²K through the external walls and 0.10 W/m²K through the roof, ensure the lifetime costs for the finished project remain low.
Successful Project
This project was far from your normal selfbuild project. Yes it had walls, floors and roof but it also had TF200 Thermo Reflex Paper, Posi Floor Joists, Loose Rafters on Glulam Ridge, Glulam Feature Truss and Loose Rafters on Steel Purlins. Therefore this project included many outstanding features. With all the above and taking into account that the site was split level, we had to be very hands on to navigate the project with numerous visits to site prior to erection to ensure co-ordination.
|

Swains Hill, Hereford
|


|

Timescale and Cost
Approx £14,700 supply and erect. The erection period took only 3 days and was fully water tight 2 days later.
Thermal Efficiency
This was looked at closely and was able to achieve 0.3W/m2K easily using timber frame
Successful Project
This was a very hands on project for the clients and they were impressed at the real benefits of timber frame, i.e. speed of build, easy to Project Manage.
|

Goodrich, Herefordshire
|


|
 |
| Timescale and Cost
This project from 2004 cost approx £20,000 supply and erect. The erection period was about 3 weeks.
Thermal Efficiency
For this project the clients chose to use 140mm timber frame. In 2004 this was one of the best options on the market
Successful Project
This quaint 3 bedroom property with a large open plan living area shows again the flexibility of timber frame
|

Gobowen, Oswestry
|
Timescale and Costs
Approx £24,150 supply and erect, with the timber frame build time of 2 1/2 weeks.
Thermal Efficiency
U-value of 0.24 W/m2K which for a project of this style and quality will achieve a good resale value and reduce ongoing cost from heating.
Successful Project
2 Storey, 5 Bedroom house, on a small development of 4 houses. It was key for the developer on this project to use timber frame , to achieve the build program.
|
 |
 |

Plot 1, Norton, Presteigne
|
Timescale and Cost:
This 4 Bedroom, 2 storey house was constructed in August 2010, covering 202m² at a cost of £10,400.00 Supply only.
Thermal Efficiency
This family house was insulated with Glass Mineral Wool to achieve a U-value of 0.25 W/m2K through the external walls and 0.2 W/m2K through the roof. Also achieving a air test of 5.1 m3/h/m2.
Successful Project
This 140mm timber frame structure utilized attic trusses to the roof area for extra storage space and they also made use of rain water harvesting.
|
|

Plot 2, Norton, Presteigne
 |
|
Timescale and Cost
This family home consist of 4 bedrooms over 2 storey’s at a cost of 22K Supply & Erect with a square meterage of 189m². This project was erected within 6 days.
Thermal Efficiency
The project made use of our supper insulated Twin Wall System to a U-value of 0.12 W/m²K through the External walls and 0.1 W/m²K through the roof. The insulation used was Warmcel recycled newspaper through the walls and Glass mineral wool through the roof zone.
Successful Project
This projected relied upon Frame Wise’s Twin Frame to insulate the house well and the only other heating that was in the house was a wood burner in the middle of the house with the chimney open to the upper part of the house (this was named a Eco Chimney). Also included in this project was the metal web joists to accommodate mechanical ventilation system.
|
 |
|

Plot 3, Norton, Presteigne
|
Timescale and Cost
This project was a one and a half storey dormer Bungalow and the Supply only element was 15k, to include a upgrade to Posi floor joists. With a squire meter area of 200m².
Thermal Efficiency
The client took the option of glass mineral wool insulation on this project and achieved 0.23W/m²K through the external walls and 0.15W/m²K through the roof.
Successful Project
The project was a 140mm timber frame, 3 bed dormer bungalow over one and half storey’s. This included double bobtail trusses on Glulam purlins and utilized Posi floor joists. The client was very happy with the space provided upstairs. They made use of a Brick outer cladding and slate on the roof.
|
|
|