Public Buildings

Flats in Torquay

Timescale and Cost

Approx £147,000.00 supply & erect. The erection period took 7 weeks (8 weeks shorter than the contract period).

Thermal Efficiency

0. 20 W/m2K through external walls with our Factory Fitted insulation operation, which they found much less time consuming on site, also helped with excellent air tightness.

Successful Project

Due to lack of space on site we endeavored to supply the Frame as and when needed, requiring careful communication between both ourselves and the client. With both a crane and telescopic fork lift on site we managed to lift the panels in place. With the client choosing factory fitted insulation, this helped lower his U-values, save space on site and reduce overall build time.

joistwallsjoist

spacer

 

Oswestry Golf Club

oswestry1
Size and Timescale

This 800m2 single storey project had a lead time of 12 weeks. We were on site for a period of 5 weeks.

Thermal Efficiency

This building had a U-value of 0.3 W/m2K, this was easy to achieve with timber frame.

Successful Project

This luxurious golf club has large elegant rooms with over height panels. The large roof area gives it a striking external appearance.

oswestry2
oswestry3

spacer

 

Anglesey County Council

anglesey1 Frame Wise supplied and erected the entrance extension as a Glulam structure. This project demonstrates the flexibility of Timber.

To find out more please read the testimonial.

anglesey2

spacer

Wharton Library

wharton1 wharton2
This unique hockey stick design was realised using I-joists for the roof.

spacer

Kite Centre, Aberystwyth

A design that allows viewing areas and balconies. This was an eco friendly build designed to complement its surroundings kite2